Information on the progress of the preparation of the state irrigation network for the vegetation period of 2018 as of April 2, 2018
Information on the progress of the preparation of the state irrigation network for the vegetation period of 2018 as of April 2, 2018

To prepare the network for the vegetation period of 2018 as of April 2, 2018, across the Republic the works were performed for the amount of 162.1 million KGS with a plan of 190.0 million KGS or 85%. These funds are used for:

- repair of canals 336.7 km with a plan of 412.8 km or 82%;

- Mechanized cleaning of canals 315.1 km, with a plan of 369.9 km or 85%;

- repair of hydraulic structures - 972 units with a plan of 1161 or 84%;

- Repair of hydroposts 932 units with a plan of 1101 or 85%;

- Repair of pumping stations 84 units with a plan of 102 or 82%;

According to the schedule of works, the preparation of the irrigation network for the growing season will be completed:

- Batken, Osh, Jalal-Abad oblasts - on April 10, 2018;

- Chui and Talas oblasts - April 20, 2018;

- Issyk-Kul and Naryn oblasts on May 1, 2018;

- Orto-Tokoy, Kirov and Papan reservoirs according to the schedule for preparation for vegetation in 2018 are ready to supply irrigation water.

Read 1138 times
Login to post comments

SWRA

 

State Water Resources Agency under Ministry of Agriculture, Forestry and Water Resources of the Kyrgyz Republic

Schedule

Working days:

Monday to Friday from 9:00 a.m to 6:00 p.m 

Weekend:

Saturday Sunday

Contacts

Address:

4 A Toktonalieva str.

720055, Bishkek, Kyrgyzstan

Phone:

+996 312 54 90-95 (Reception)

Fax:  

+996 312 54 90-94

E-mail:

basssein@mail.ru

 

Top
We use cookies to improve our website. By continuing to use this website, you are giving consent to cookies being used. More details…